CEA-Series gages supplied with Option P2 can be installed in a wide variety of applications. General gage installation procedures provided in Vishay Measurements Group technical literature, VideoTech Libraries , and training programs provide a sound foundation; however, the need for leadwire attachment after gage bonding is eliminated by Option P2. Although application conditions may dictate certain installation procedures, the following guidelines are recommended for maximum performance. They supplement any standard procedures when installing gages with preattached leadwires.


  Gage Handling and Cable Support
  Surface Preparation
  Gage Bonding
  Protective Coatings
  Strain Relief