Common Leadwire Attachment
|
Gage Handling and Cable Support
After removing the gage and its protective window
from the pouch in the plastic box, hold the
gage/cable assembly by the cable bundle. Release a
comfortable working length of cable and place the
gage on a chemically clean surface. Temporarily
secure the remainder of the bundle before removing
the gage from its protective window with a pair of
M-LINE BTW-1
Blunt-nosed Tweezers
.
Apply a strip of
M-LINE PCT-2A
Cellophane Tape
to the gage face. This transfer tape should be
applied in the direction transverse to the leadwires.
When ready to bond the gage, carefully lift the tape
from the surface at a shallow angle. Unsecure the
cable bundle and hold the gage/tape assembly by the
bundle when moving it to the installation site.
Page 2 of 6
|
|